Client: Czech Development Agency
Location: BiH
Time period: October – November 2019
About: Our role as a subcontractor and local implementation unit for parent company Dekonta a.s., Czech Republic, was integral to the successful completion of the project aimed at constructing a Constructed Wetland (CW) treatment plant in the municipality of Bogušići. This CW facility is connected to a newly built sewage system and achieved several key objectives:
- Environmental Improvement: Significantly enhancing the environmental conditions in the municipality of Bogušići.
- Awareness Campaign: Raising awareness about environmental issues among residents of Bogušići and Goražde.
- Innovative CW Design: Implementing a second-generation Constructed Wetland designed with DEKONTA’s innovations. This pilot facility not only serves as a model for future projects within Bosnia and Herzegovina but also acts as a showcase to promote similar initiatives nationwide.